Chitral/Shandur Road Project Targets December 2026 Completion as Construction Continues Across All Four Sections

Chitral/Shandur Road Project Targets December 2026 Completion as Construction Continues Across All Four Sections

▫️153 kilometre National Highway N-140 requires Rs 4.20 billion during FY2026-27 to meet the revised completion deadline

Chitral : ReNews PakistanThe federal government has set December 2026 as the revised completion deadline for the 153-kilometre Chitral–Booni–Mastuj–Shandur Road, a strategically important highway project aimed at improving connectivity b...

Chitral : ReNews Pakistan
The federal government has set December 2026 as the revised completion deadline for the 153-kilometre Chitral–Booni–Mastuj–Shandur Road, a strategically important highway project aimed at improving connectivity between Upper Chitral and the Shandur region.
According to official documents, the project requires Rs4.20 billion during the 2026-27 fiscal year to achieve its revised target. Authorities have already spent Rs6.59 billion on the road's construction since work began.
The route connects Chitral, Pret, Booni, Mastuj, Shaidas and Shandur, providing an important transport corridor for local communities, tourism and regional economic activity. Following its federalisation in May 2020, the road was designated National Highway N-140, bringing it under the national highway network.
To facilitate construction, the project has been divided into four separate work packages, with work currently in progress on all sections. However, construction progress varies considerably across the different segments.
The first package, extending from Chitral to Pret, has recorded the highest level of progress, with 47.54 percent of work completed. The second package, covering the Pret–Booni section, has reached 34.77 percent completion.
Meanwhile, the third package, from Booni to Shaidas, stands at 38.16 percent completion. The fourth and final package, connecting Shaidas with Shandur, has achieved 29.78 percent progress, making it the least advanced section of the project.
The Chitral–Shandur Road was originally scheduled for completion between 2023 and 2024, but construction delays resulted in a revised timeline. With the government now targeting completion by December 2026, the timely release of development funds and sustained construction activity will be critical to meeting the new deadline.
Once completed, the upgraded highway is expected to improve year-round accessibility, facilitate tourism to the internationally renowned Shandur Pass, reduce travel times, strengthen regional trade and provide safer transportation for residents across Upper Chitral.
Bahawalpur Commissioner Directs Officials to Ensure Quality Construction of Bandra Pulli–Sahulat Bazaar Road

Bahawalpur Commissioner Directs Officials to Ensure Quality Construction of Bandra Pulli–Sahulat Bazaar Road

▫️ Highways Department instructed to complete road-base preparation, construct durable shoulders and install high-quality tuff tiles

Bahawalpur Division Commissioner Irfan Ali Kathia has inspected ongoing construction work on the road connecting Bandra Pulli with Sahulat Bazaar, directing officials to ensure the use of high-quality materials and strict compliance with...

Sindh Sets Rs 25.5 bn Karachi Property Tax Collection Target

Sindh Sets Rs 25.5 bn Karachi Property Tax Collection Target

▫️ The target covers Karachi’s 25 town municipal corporations. A World Bank note released on 25 November says the city’s property database has grown to 4.5 million records, while tax compliance stands at 22 per cent.

The Sindh government has set a target to increase annual property tax collection across Karachi’s 25 town municipal corporations from Rs 2.

Lahore Imposes Restrictions on Residential and Commercial Construction Along Tarogil Road

Lahore Imposes Restrictions on Residential and Commercial Construction Along Tarogil Road

▫️ Metropolitan Corporation Lahore issues public notice over unauthorised construction in Raiwind's Nishtar Zone

The Metropolitan Corporation Lahore (MCL) has issued a public notice restricting unauthorised residential and commercial construction along Tarogil Road in the Ishtar Zone of Raiwind, Lahore.

Punjab Approves Rs 5.886 Billion Project to Restore Historic Buildings and Markets in Rawalpindi

Punjab Approves Rs 5.886 Billion Project to Restore Historic Buildings and Markets in Rawalpindi

▫️ Restoration plan includes heritage conservation, pedestrian-friendly streets and underground electricity networks

Rawalpindi | ReNews Punjab Correspondent

Margalla Avenue Extension and Sangjani Interchange Project Reaches 43% Completion

Margalla Avenue Extension and Sangjani Interchange Project Reaches 43% Completion

▫️ Major road project will improve connectivity between N-5, M-1, Islamabad International Airport and Khyber Pakhtunkhwa

The Capital Development Authority (CDA) has reported 43% overall progress on the Margalla Avenue Extension and Sangjani Interchange project, which aims to improve road connectivity between the N-5 National Highway and M-1 Motorway.

AJK Assembly Welcomes 100-Day Development Plan for Infrastructure and Public Services

AJK Assembly Welcomes 100-Day Development Plan for Infrastructure and Public Services

▫️ Resolution highlights proposed improvements in road networks, healthcare, education, transport and tourism across Azad Kashmir

The Azad Jammu and Kashmir (AJK) Legislative Assembly has welcomed the announcement of a 100-day development plan aimed at improving infrastructure and public services across the region.

NHA to Construct 1.56 km Maloopa Tunnel as Development Work Accelerates on Jaglot–Skardu Road

NHA to Construct 1.56 km Maloopa Tunnel as Development Work Accelerates on Jaglot–Skardu Road

▫️ New tunnel, landslide protection structures, road lighting and rescue services planned to improve travel safety

Federal Minister for Communications Abdul Aleem Khan has inspected ongoing construction and infrastructure development projects along the Jaglot–Skardu Road in Gilgit-Baltistan.

CDA Approves Islamabad Avenue and Plans Commercial Development Along 3.8km Road

CDA Approves Islamabad Avenue and Plans Commercial Development Along 3.8km Road

▫️ New road linking Park Road with Margalla Enclave to feature commercial and mixed-use projects under proposed building regulations

Islamabad | ReNews Capital CorrespondentThe Capital Development Authority (CDA) Board has approved the name Islamabad Avenue for the 3.8-kilometre road under construction between Park Road and Margalla Enclave in Islamabad. The board als...

Federal Minister Orders Early Completion of Lowari Tunnel and Chitral Highway Projects

Federal Minister Orders Early Completion of Lowari Tunnel and Chitral Highway Projects

▫️ Completion of road projects aimed at improving regional connectivity, supporting tourism and facilitating local communities

Federal Minister for Communications Abdul Aleem Khan has directed the authorities concerned to accelerate the remaining construction and development works on the Lowari Tunnel and Chitral Highway projects.

More City and District Real Estate News

More Real Estate News

National Real Estate News

See All →

Global Real Estate News

See All →

Corporate Real Estate News

See All →

Social Real Estate News

See All →

Real Estate Insights

See All →

Arazi Nama

See All →