▫️ Annual Development Programme Provides Just 2.2% of Total Project Cost, Raising Concerns Over Funding Availability and Timely Completion
ABBOTTABAD (ReNews Pakistan): According to project information reported from the Annual Development Programme (ADP) 2026/27 of the Planning and Development Department, Government of Khyber Pakhtunkhwa, the Rs 1 billion Qalandarabad to Th...
ABBOTTABAD (ReNews Pakistan): According to project information reported from the Annual Development Programme (ADP) 2026/27 of the Planning and Development Department, Government of Khyber Pakhtunkhwa, the Rs 1 billion Qalandarabad to Thandiani Road Project in Abbottabad has been allocated Rs 22 million for the current financial year, representing just 2.2 per cent of its estimated total cost.The project, included in the provincial government’s Khushal Hazara Programme, aims to improve road connectivity between the Karakoram Highway at Qalandarabad and the mountainous areas towards Thandiani, one of Abbottabad’s important tourist destinations.
Identified as Scheme No. 1851/261051, the project is officially titled Construction/Rehabilitation of Road from KKH Qalandarabad to Thandiyani Road via Tarnawai, Trerri, Maira Rehmat Khan Road, District Abbottabad.The proposed road covers approximately 15.30 kilometres, comprising the rehabilitation and improvement of an existing eight kilometre section from Qalandarabad (Mera Ban) to Riyala and the construction of a new 7.30 kilometre road from Riyala to Gali Mera Rehmat Khan through Pagha, Tareri and Shehzadey.The Communication and Works (C&W) Department, Government of Khyber Pakhtunkhwa, is identified as the sponsoring department, while C&W Highway Division Abbottabad is responsible for executing the project.The reported implementation period is 36 months, with cost estimates prepared according to MRS 2025 First Bi-Annual rates.
Financial Allocations
The project’s estimated PC-I cost stands at Rs 1,000 million.According to the reported development programme figures, Rs 22 million has been allocated for financial year 2026/27, while Rs 489 million is envisaged for each of the following two financial years, 2027/28 and 2028/29.This means that approximately 97.8 per cent of the project’s estimated expenditure is scheduled for subsequent financial years.Although the allocation reflects the proposed financial phasing, the project’s timely completion will depend on the release of funds, administrative approvals and the commencement and progress of construction activities.
Connectivity and Regional Development
The proposed road is expected to improve accessibility between Qalandarabad, Tarnawai, Trerri, Maira Rehmat Khan and surrounding mountain settlements.
Through the existing road network, improved connectivity could also facilitate onward access towards Havelian Interchange on the Hazara Motorway (M-15), connecting local communities with wider regional transport routes.Better road infrastructure could reduce transportation difficulties for residents, improve the movement of agricultural products and commercial goods, and support economic activity in remote parts of Abbottabad district.
Tourism and Real Estate Potential
Thandiani is recognised for its scenic mountain landscapes, pine forests and tourism potential.
Improved access to the area could encourage investment in hotels, guest houses, resorts, restaurants and other tourism-related facilities.
The proposed road could also improve accessibility to residential and commercial properties along the route, potentially creating opportunities for local businesses and real estate development.