▫️Road widened to 32 feet along 1.4 kilometre stretch; major drainage, sewerage, pedestrian and street lighting works completed
Karachi : ReNews PakistanKarachi Mayor Barrister Murtaza Wahab has inaugurated a Rs 360 million rehabilitation and improvement project on Jahangir Road, covering the section between Guru Mandir and Teen Hatti, with the initiative aimed a...
Karachi Mayor Barrister Murtaza Wahab has inaugurated a Rs 360 million rehabilitation and improvement project on Jahangir Road, covering the section between Guru Mandir and Teen Hatti, with the initiative aimed at improving traffic flow, road infrastructure and rainwater drainage in one of the city’s busy corridors.
According to a statement issued by the Karachi Metropolitan Corporation (KMC), the completed project covers approximately 1.4 kilometres of the two-way Jahangir Road. As part of the rehabilitation, the road has been widened from 26 feet to 32 feet to provide additional space for traffic and facilitate smoother movement of vehicles.
The project involved extensive pavement and asphalt works. Contractors installed around 252,000 square feet of 80 millimetre paving blocks and 70,000 square feet of 60 millimetre paving blocks. In addition, approximately 50,000 square feet each of asphalt base course and asphalt concrete were completed as part of the road reconstruction.
A major component of the project was the rehabilitation and upgrading of the drainage and sewerage infrastructure along the road. Damaged sewerage lines were repaired, while more than 11,800 running feet of trenching was completed for the installation of a 36 inch diameter stormwater drainage line.
The upgraded drainage network has also been connected to the Lyari River to improve the disposal of rainwater and reduce the risk of water accumulation on the road during heavy rainfall. The project included the construction of 45 manholes to support the drainage system and facilitate future maintenance and access.
The rehabilitation work also focused on improving road safety and pedestrian facilities. Lane markings, kerb blocks and footpaths were completed on both sides of Jahangir Road, providing improved facilities for pedestrians while giving the rehabilitated corridor a more organized layout.
To enhance visibility and improve the overall environment of the road, 80 new solar powered streetlights have been installed. Six damaged light poles were also replaced during the project.
Speaking at the inauguration, Mayor Murtaza Wahab said the rehabilitation of Jahangir Road would help improve traffic movement in the area while also strengthening the drainage system to ensure more effective rainwater disposal.
The project is expected to provide a combination of improved road capacity, upgraded drainage and sewerage infrastructure, better pedestrian facilities and enhanced street lighting for residents and commuters using the Jahangir Road corridor.