Published: October 15, 2026 - 5:01 PM
KP Mosque Solarisation Project Faces Allegations of Procurement and Contract Irregularities
خیبرپختونخوا میں مساجد کی سولرائزیشن کے منصوبے میں خریداری اور ٹھیکوں کی بے ضابطگیوں کے الزامات
▫️ Winning bids for seven packages covering 2,490 mosques reportedly exceeded official estimates, adding more than Rs 500 million to project costs
Peshawar | ReNews PakistanThe Khyber Pakhtunkhwa government’s mosque solarisation programme has come under scrutiny following allegations of irregularities in tendering, cost estimates and contract management.
The Khyber Pakhtunkhwa government’s mosque solarisation programme has come under scrutiny following allegations of irregularities in tendering, cost estimates and contract management. The provincial energy development organisation has rejected suggestions of unlawful favouritism, maintaining that established procurement procedures were followed.
According to documents cited in a media report, successful bids for all seven packages covering the solarisation of 2,490 mosques during the Pakistan Tehreek-e-Insaf government were between 7.98% and 10.99% higher than official estimates. The difference reportedly placed an additional burden of more than Rs 500 million on the public exchequer.
The report also raised questions about the participation of two companies that were initially disqualified during prequalification. Both firms were subsequently allowed to rejoin the tender process after filing complaints. Their readmission has become one of the procurement decisions highlighted in the allegations.
Cost calculations have drawn further scrutiny. The estimated cost per solar unit reportedly differed by approximately Rs 156,000 from that of an earlier project carried out by the National Radio and Telecommunication Corporation (NRTC). The reported comparison has raised questions about the basis used to prepare estimates for the subsequent work.
Separately, the documents reportedly identified delays in NRTC’s earlier contract and cited potential penalties of around Rs 586 million. According to the report, the penalties were not imposed, while NRTC received another contract, valued at an estimated Rs 419.1 million, to solarise 500 mosques.
These claims have brought the enforcement of contractual obligations into focus, alongside questions over procurement decisions and project costs. The reported penalty figure represents a potential contractual liability rather than a confirmed recovery.
Responding to the allegations, the Pakhtunkhwa Energy Development Organization (PEDO) said the project had complied with all legal requirements and transparency standards. It maintained that bids were assessed under established rules and that no company had received an unlawful benefit.
PEDO attributed implementation delays to funding constraints and administrative issues. Its position disputes the allegations of improper handling of the project.
The provincial government has set an overall target of converting 7,500 mosques to solar power. The allegations concern procurement and contract management within the programme; the supplied report does not establish a final finding of corruption.