DG LDA Reviews Construction Work on Data Darbar Expansion Project and Nasir Bagh Parking Plaza

DG LDA Reviews Construction Work on Data Darbar Expansion Project and Nasir Bagh Parking Plaza

▫️Nasir Bagh underground parking plaza 65 percent complete; DG directs installation of international standard parking, fire safety and signage systems

Lahore: [Riaz Hussain ReNews Pakistan]Director General Lahore Development Authority (LDA) Tahir Farooq conducted a detailed visit to the Data Darbar expansion project, Bhati Chowk underpass and the underground Nasir Bagh parking plaza to...

Lahore: Riaz Hussain | ReNews Pakistan
Director General Lahore Development Authority (LDA) Tahir Farooq conducted a detailed visit to the Data Darbar expansion project, Bhati Chowk underpass and the underground Nasir Bagh parking plaza to review the pace, quality and progress of ongoing construction work.
Advisor to the Chief Minister Punjab Zeeshan Malik accompanied him during the visit, while TEPA Chief Engineer Iqrar Hussain and project directors briefed the delegation on various projects.
Officials said development work on the Data Darbar expansion project is progressing rapidly. Tile work and greenery are underway at the shrine’s plaza, while the facade upgradation of properties around Data Darbar is also being carried out at a fast pace. Finishing work on the parking area, toilet block and pedestrian underpass is also continuing simultaneously.
Advisor to the Chief Minister Punjab Zeeshan Malik appreciated the development work around the Data Darbar expansion project and said the completion of the project and Bhati Chowk underpass would provide major convenience to visitors and citizens by improving access, safety and mobility.
Officials briefed that work is underway simultaneously on both ramps of the Bhati Chowk underpass, while construction on the underpass barrel and retaining walls is being carried out round the clock. DG LDA Tahir Farooq directed the authorities concerned to further accelerate work on the Bhati Chowk underpass so citizens can benefit from the facility at the earliest.
Later, the DG LDA visited the underground Nasir Bagh parking plaza, where he was informed that nearly 65 percent of the project has been completed. According to the briefing, the grey structure of Basement Two has been completed, while work on Basement One is currently underway. The complete roof of Basement One is expected to be laid in the coming days.
Tahir Farooq reviewed the construction quality of the parking plaza in detail and directed that the parking management system, signage, fire alarm system and other safety arrangements be installed in line with international standards to provide citizens with a modern and secure parking facility.
He also instructed officials to ensure strict implementation of safety SOPs during construction activities in the monsoon season to protect workers and the public.
At the end of the visit, DG LDA Tahir Farooq planted a sapling at Nasir Bagh under the ongoing plantation campaign. Officials said more than 1,000 saplings would be planted in Nasir Bagh to promote greenery and improve the city’s environment.
AJK Assembly Welcomes 100-Day Development Plan for Infrastructure and Public Services

AJK Assembly Welcomes 100-Day Development Plan for Infrastructure and Public Services

▫️ Resolution highlights proposed improvements in road networks, healthcare, education, transport and tourism across Azad Kashmir

The Azad Jammu and Kashmir (AJK) Legislative Assembly has welcomed the announcement of a 100-day development plan aimed at improving infrastructure and public services across the region.

NHA to Construct 1.56 km Malupa Tunnel as Development Work Accelerates on Jaglot–Skardu Road

NHA to Construct 1.56 km Malupa Tunnel as Development Work Accelerates on Jaglot–Skardu Road

▫️ New tunnel, landslide protection structures, road lighting and rescue services planned to improve travel safety

Federal Minister for Communications Abdul Aleem Khan has inspected ongoing construction and infrastructure development projects along the Jaglot–Skardu Road in Gilgit-Baltistan.

CDA Approves Islamabad Avenue and Plans Commercial Development Along 3.8km Road

CDA Approves Islamabad Avenue and Plans Commercial Development Along 3.8km Road

▫️ New road linking Park Road with Margalla Enclave to feature commercial and mixed-use projects under proposed building regulations

Islamabad | ReNews Capital CorrespondentThe Capital Development Authority (CDA) Board has approved the name Islamabad Avenue for the 3.8-kilometre road under construction between Park Road and Margalla Enclave in Islamabad. The board als...

Federal Minister Orders Early Completion of Lowari Tunnel and Chitral Highway Projects

Federal Minister Orders Early Completion of Lowari Tunnel and Chitral Highway Projects

▫️ Completion of road projects aimed at improving regional connectivity, supporting tourism and facilitating local communities

Federal Minister for Communications Abdul Aleem Khan has directed the authorities concerned to accelerate the remaining construction and development works on the Lowari Tunnel and Chitral Highway projects.

LDA to Auction Commercial Plots in Lahore Technology Park on December 3

LDA to Auction Commercial Plots in Lahore Technology Park on December 3

▫️ Balloting for Pine Axis and Pine Executive plots scheduled for December 10 as LDA expands investment opportunities

The Lahore Development Authority (LDA) has announced that commercial plots in Lahore Technology Park, located on Ferozepur Road near Arfa Karim Software and Technology Tower, will be auctioned on December 3, 2026, at Expo Centre, Johar T...

KP Plans Independent Commission to Resolve Land Ownership Dispute Between Kolai-Palas and Battagram Tribes

KP Plans Independent Commission to Resolve Land Ownership Dispute Between Kolai-Palas and Battagram Tribes

▫️ Hazara administration to seek provincial approval for an impartial settlement commission to determine disputed land ownership

The Hazara divisional administration has decided to approach the Khyber Pakhtunkhwa government for the establishment of an independent settlement commission to resolve a longstanding land ownership dispute between rival tribes in Kolai-P...

FGEHA Approves Relocation of Three Islamabad Plots to Preserve 300-Year-Old Trees

FGEHA Approves Relocation of Three Islamabad Plots to Preserve 300-Year-Old Trees

▫️ Three one-kanal residential plots in Sector G-14/3 to be shifted as authority plans a park around two historic banyan trees

The Federal Government Employees Housing Authority (FGEHA) has approved in principle the relocation of three residential plots in Islamabad's Sector G-14/3 to protect two banyan trees estimated to be around 300 years old.

Pakistan Railways Issues Eviction Notices to 147 Property Owners in Hyderabad Over Land Ownership Dispute

Pakistan Railways Issues Eviction Notices to 147 Property Owners in Hyderabad Over Land Ownership Dispute

▫️ Railways claims more than 1,152 acres across Hyderabad district as property owners question eviction notices and demand legal protection

Pakistan Railways has issued approximately 147 eviction notices to owners and occupants of residential and commercial properties in Hyderabad, alleging unauthorised occupation of railway land.

Punjab Signs Agreements for Modern Toll Plazas on 318 Kilometres of Major Roads

Punjab Signs Agreements for Modern Toll Plazas on 318 Kilometres of Major Roads

▫️ Ten toll plazas to be developed across Muridke–Narowal–Shakargarh Road, Faisalabad–Samundri–Rajana Road and Faisalabad Ring Road

The Punjab government has signed agreements with private companies to develop and operate ten modern toll plazas across 318 kilometres of major road networks.

More City and District Real Estate News

More Real Estate News

National Real Estate News

See All →

Global Real Estate News

See All →

Corporate Real Estate News

See All →

Social Real Estate News

See All →

Real Estate Insights

See All →

Arazi Nama

See All →