Published: July 11, 2026 - 4:47 PM
CDA Plans PPP Model to Revive PKR 15.3 Billion Nilore Heights Housing Project
سی ڈی اے کا 15.3 ارب روپے کے نیلور ہائٹس منصوبے کو پی پی پی ماڈل کے تحت بحال کرنے پر غور
▫️Special CDA Board meeting to decide future of the stalled apartment scheme after federal government removes NPHDA from the project
Islamabad: [ReNews Pakistan]The Capital Development Authority (CDA) is preparing to revive the long delayed Nilore Heights Apartments project by exploring a Public Private Partnership (PPP) model, following the federal government's decis...
The Capital Development Authority (CDA) is preparing to revive the long delayed Nilore Heights Apartments project by exploring a Public Private Partnership (PPP) model, following the federal government's decision to withdraw the Naya Pakistan Housing and Development Authority (NPHDA) from the housing scheme.
According to CDA officials, Chairman Lieutenant General (Retd.) Sohail Ashraf has directed that a special meeting of the CDA Board be convened to determine the future course of the multibillion rupee project. The meeting is expected to evaluate various options for completing the development, including the possibility of engaging private-sector partners through a PPP framework.
Officials said the Authority will seek technical and financial input from professional consultancy firms before making a final decision. With the NPHDA no longer associated with the project, the CDA has been granted full authority to execute and manage the scheme independently.
The Nilore Heights Apartments project was launched in 2021 as part of the government's affordable housing initiative and was originally scheduled for completion by June 2023. However, construction came to a halt after the grey structures of 60 apartment blocks were completed, leaving the project partially finished.
According to officials, the suspension occurred after the NPHDA failed to fulfil its financial commitments, despite the CDA having already invested billions of rupees in infrastructure and construction. Since then, the unfinished buildings have remained idle, raising concerns about structural deterioration and increasing maintenance costs.
A Federal Audit Report for the financial year 2024-25 revealed that the project carries an approved cost of PKR 15.3 billion, of which PKR 8.3 billion had been released by June 30, 2024. The report noted that the prolonged delay has postponed an estimated PKR 14 billion in anticipated revenue and identified NPHDA's inability to meet its financial obligations as the primary reason behind the project's suspension.
Officials further disclosed that the first phase of the development, comprising approximately 2,400 apartments, has largely completed its structural work, with only finishing and interior works remaining before the units can be delivered. Meanwhile, construction of the second phase was halted during the foundation stage and will require fresh planning before work can resume.
CDA authorities believe that an early decision on the project's future is essential to safeguard the existing structures, minimise further financial losses, and ensure the timely completion of one of Islamabad's most significant public housing developments. The Authority expects the upcoming Board meeting to establish a clear roadmap for restarting construction and bringing the long-stalled project back on track.